Power grid's isolated operation test to take place in Russia's Kaliningrad in September
"We view Kaliningrad's isolated operation test as mutual preparation for the Baltic states' synchronization with continental Europe's networks. Technically, this test will not affect the operator of Lithuania's power system," Daivis Virbickas, CEO of Litgrid, said in a statement.
In his words, preparations from the Kaliningrad test have been made in advance and during its times, Litgrid will operate under a prepared working plan whose main goal is "to ensure the system's reliable and coordinate operation with the neighboring countries' operators".
The test in Kaliningrad is scheduled for September 12, Litgrid says, and it should take 8 hours. Trade in electricity imported from Kaliningrad will be suspended for that time.
The first test of this kind took place in Kaliningrad in late May, 2019 and lasted for 72 hours. Before that, several short tests of 15 minutes were performed.
Kaliningrad plans to carry out isolated operation tests every year up until Lithuania and the other Baltic states will disconnected from the post-Soviet BRELL system, which is scheduled to take place by 2025.
- 29.12.2020 Linde Gas открывает завод в Кедайняйской СЭЗ
- 29.12.2020 Lithuanian president signs 2021 budget bill into law
- 29.12.2020 Президент Литвы утвердил бюджет 2021 года
- 28.12.2020
- 28.12.2020 Tartu to support students' solar car project
- 28.12.2020 Owner of Kunda Nordic Tsement to install full-scale CCS facility in Norway
- 23.12.2020 В Литве учреждены еще две белорусских компании
- 23.12.2020 Lidl Lithuania to destroy Salmonella-contaminated eggs from Ukraine
- 23.12.2020 LTG Infra gets green light to build Rail Baltica section from Kaunas to Latvian border
- 22.12.2020 LTG Infra дает зеленый свет строительству Rail Baltica от Каунаса до границы с Латвией