Hitachi fails to stop Vilnius Cogeneration Power Plant contractor tender
A consortium of
Switzerland's Hitachi Zosen Inova, a
Hitachi subsidiary, and its partner Abener
Energia of Spain that were participating in the tender has filed a lawsuit
to a Vilnius court, asking to annul the results and recognize it as the winner.
On Friday, the court
rejected the plea to suspend the signing of the contract with a consortium
headed by Germany's Steinmuller Babcock
Environment that won the tender, told the court official Raimonda Jagminaite.
Ernesta Dapkiene of the Lithuania's state-owned energy
group Lietuvos Energija (Lithuanian
Energy) implementing the tender told that the offer of Hitachi Zosen Inova and Abener
Energia had come in second.
The power plant should
be built by the consortium of Steinmuller
Babcock Environment, which includes Budimex,
one of Poland's largest engineering and infrastructure construction groups, and
Lithuania's gas pipeline construction company Kauno Dujotekio Statyba, for 178.29 mln euros. The plant's biofuel
burning equipment and supplies infrastructure should be constructed by Poland's
energy object builder Rafako for 149.65 mln euros.
Estimated at a total of
345 mln euros, the power plant project will for now be developed by Lietuvos Energija, which will also